Telangana: Saraswati Pushkaralu works postponed

Warangal: In less than 48 hours, most people have not completed Saraswati Pushkaralu of Kaleshwaram in Mahadevpur Mandal in Jayashankar Bhupalpally. The event will begin on May 15 and end on May 24.

The government has approved Rs 250 crore as they have been working on 65 development projects before May 4. The deadline was missed and a deadline of May 10 was given. Four days after the update deadline, many works are yet to be tried due to negligence by officials and contacts.

Incomplete works include 20-foot statues of Saraswati Devi and Godavari Aarti Ghats, arches at the entrance, concrete floors, lighting and steel railings. Devotees can be difficult because permanent rest and locker rooms, drinking water tanks, close to roads, pilgrim sheds and queue lines are not yet ready. The composite wall and the Prasadan preparation hall are not ready yet.

Kaleshwaran Temple officials told Deccan Chronicle It said that despite the government approved funds a month and a half ago, a lack of coordination between departments and contractors has led to a slow pace of work.

In a recent visit, IT Minister Duddilla Sridhar Babu layed off employees for poor quality work, and even though two deadlines were completed, the work was not completed.

He noted that there was little time left, and officials rushed into work by building temporary and temporary buildings.

This is the first Saraswati Pushkaralu held after the formation of Telangana State. The last event was not separated in Andhra Pradesh during the parliamentary government rule in 2013.

The government allocated 28 works of Rs 996 crore to the donation department, the irrigation department had four works of Rs 531 crore, Rs 301 crore, seven works, seven jobs, Rs 228 crore to the Panchayat Raj Department, 15 jobs and Rs 99.39 electrical departments were given to Mission Bhagiratha and the water supply department and the water supply department, providing Rs 1199.39 for the works of Rs 119.39 for Lakh. After Pushkaralu in Kaleshwaram, another Rs 4 crore development project is allocated as development project.